A contractor uses the percentage-of-completion method for revenue recognition. If a job is 40% complete and the total contract value is $200,000, recognized revenue to date is:
a.$40,000
b.$80,000
c.$120,000
d.$200,000
Explanation
Under percentage-of-completion, revenue = contract value × percentage complete = $200,000 × 40% = $80,000. This method matches revenue to the work actually performed.
Practice all 690 questions free — no signup required.
Related questions on this topic
- Which financial statement shows a contractor's assets, liabilities, and equity at a specific point in time?
- A contractor's accounts receivable are growing while cash on hand is shrinking. This most likely indicates:
- Which type of insurance protects a contractor if a third party is injured on the job site?
- What is the purpose of a "retainage" or "retention" clause in a construction contract?
- A contractor's current ratio is 0.8. This means:
- Before starting a project, a contractor should prepare a schedule of values in order to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review