Contracts & ExecutionQuestion 60 of 1632100% of test-takers answer this correctly

On a home improvement contract without a payment and performance bond, when may the contractor collect the final payment?

a.When the contracted work is complete
b.When 50% of the work is complete
c.After all materials are delivered to the site
d.At the start of the project

Want narrated lessons as well as practice? Learn it on the board: CSLB Law and Business · Try Chapter 2 free

Explanation

B&P §7159.5(a)(5): apart from a down payment, a home improvement contractor may neither request nor accept payment beyond the value of the work performed or material delivered, so the final payment waits until the contracted work is done. Option (b) collects the balance at the halfway point. Option (c) pays for labor not yet performed: delivered materials justify payment for their value only. At the start (d), only a down payment is allowed, and it cannot exceed $1,000 or 10 percent, whichever is less (§7159.5(a)(3)). A contractor furnishing a qualifying bond is exempt from these limits (§7159.5(a)(8)).

Law Reference: Bus. & Prof. Code §7159.5(a)(3), (a)(5), (a)(8)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $27.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $27.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)