On a home improvement contract without a payment and performance bond, when may the contractor collect the final payment?
Want narrated lessons as well as practice? Learn it on the board: CSLB Law and Business · Try Chapter 2 free
Explanation
B&P §7159.5(a)(5): apart from a down payment, a home improvement contractor may neither request nor accept payment beyond the value of the work performed or material delivered, so the final payment waits until the contracted work is done. Option (b) collects the balance at the halfway point. Option (c) pays for labor not yet performed: delivered materials justify payment for their value only. At the start (d), only a down payment is allowed, and it cannot exceed $1,000 or 10 percent, whichever is less (§7159.5(a)(3)). A contractor furnishing a qualifying bond is exempt from these limits (§7159.5(a)(8)).
Law Reference: Bus. & Prof. Code §7159.5(a)(3), (a)(5), (a)(8)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $27.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $27.99 →
Related questions on this topic
- A homeowner can cancel a home improvement contract that was solicited at their home within:
- Which of the following MUST be included in a California home improvement contract?
- A contractor and homeowner agree to change the scope of work during a project. This agreement must be:
- Which statement about arbitration clauses in construction contracts is TRUE?
- A contractor abandons a job without justification after receiving a substantial deposit. The contractor may face:
- Who is primarily responsible for obtaining building permits on a construction project?
Last reviewed: · editorial process