Contracts & ExecutionQuestion 59 of 690
A contractor and homeowner agree to change the scope of work during a project. This agreement must be:
a.Verbal, confirmed by a handshake
b.Written and signed by both parties before work begins
c.Approved by the local building department
d.Filed with CSLB within 10 days
Explanation
All changes to a home improvement contract must be documented in a written change order signed by both the contractor and homeowner before the changed work begins.
Law Reference: Bus. & Prof. Code §7159(d)Practice all 690 questions free — no signup required.
Related questions on this topic
- Under California law, a home improvement contract is required for residential work when the total contract price (labor AND materials) is at least:
- A homeowner can cancel a home improvement contract that was solicited at their home within:
- Which of the following MUST be included in a California home improvement contract?
- A contractor may demand final payment from the homeowner:
- Which statement about arbitration clauses in construction contracts is TRUE?
- A contractor abandons a job without justification after receiving a substantial deposit. The contractor may face:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review