Contracts & ExecutionQuestion 59 of 1605

A contractor and homeowner agree to change the scope of work during a project. This agreement must be:

a.Verbal, confirmed by a handshake
b.Written and signed by both parties before work begins
c.Approved by the local building department
d.Filed with CSLB within 10 days

Explanation

All changes to a home improvement contract must be documented in a written change order signed by both the contractor and homeowner before the changed work begins.

Law Reference: Bus. & Prof. Code §7159(d)

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report