A contractor and homeowner agree to change the scope of work during a project. This agreement must be:
Explanation
B&P §7159(d) requires a home improvement contract and any change to it to be in writing and signed by the parties before the work covered by the change begins, and §7159(c)(5) says a change-order form becomes part of the contract only on those terms. An invoice sent afterwards documents a bill, not an agreement made in advance. The building department reviews code compliance and issues permits; it has no role in making a price change enforceable between owner and contractor. And no section requires change orders to be filed with CSLB, on a 10-day clock or any other.
Law Reference: B&P Code §7159(c)(5), (d)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- Under California law, a home improvement contract is required for residential work when the total contract price (labor AND materials) is at least:
- A homeowner can cancel a home improvement contract that was solicited at their home within:
- Which of the following MUST be included in a California home improvement contract?
- A contractor may demand final payment from the homeowner:
- Which statement about arbitration clauses in construction contracts is TRUE?
- A contractor abandons a job without justification after receiving a substantial deposit. The contractor may face:
Last reviewed: · editorial process