Contracts & ExecutionQuestion 59 of 1632

A contractor and homeowner agree to change the scope of work during a project. This agreement must be:

a.Verbal, then confirmed on the next invoice sent to the owner
b.Written and signed by both parties before the changed work starts
c.Approved by the local building department before it takes effect
d.Filed with CSLB within 10 days of the price increase it causes

Explanation

B&P §7159(d) requires a home improvement contract and any change to it to be in writing and signed by the parties before the work covered by the change begins, and §7159(c)(5) says a change-order form becomes part of the contract only on those terms. An invoice sent afterwards documents a bill, not an agreement made in advance. The building department reviews code compliance and issues permits; it has no role in making a price change enforceable between owner and contractor. And no section requires change orders to be filed with CSLB, on a 10-day clock or any other.

Law Reference: B&P Code §7159(c)(5), (d)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report