Planning & EstimatingCâu 639 / 700

During interior work, in what order must inspections generally occur before the walls are closed up?

a.Rough framing and rough mechanical/electrical/plumbing are inspected and approved before insulation, and insulation is inspected before drywall covers it.
b.Insulation is installed and inspected first, then rough framing, then the MEP rough-in.
c.Drywall may be hung before the rough MEP inspection to keep the schedule moving.
d.Only a single final inspection is required; the intermediate inspections are optional.

Giải thích

Correct: work is inspected while still visible. Rough framing and rough MEP are approved first, then insulation is installed and inspected, and only then is drywall hung to cover everything. Installing insulation before framing/MEP approval, hanging drywall before rough MEP, or skipping intermediate inspections would conceal work that must be inspected first.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi