Core TradesCâu 64 / 700
Fresh concrete is being placed into a tall wall form at a high rate on a cool day. The crew is concerned about lateral pressure on the forms. Which factor will MOST increase the lateral concrete pressure on the formwork?
a.Using a lower-slump, stiffer mix
b.Placing at a slower rate
c.Warmer concrete temperature
d.A faster rate of placement
Giải thích
Lateral form pressure increases with a faster rate of vertical rise because more of the concrete remains fluid before it stiffens. Slower placement, stiffer/lower-slump mixes, and warmer concrete (faster set) all reduce peak pressure. A faster placement rate is the dominant factor increasing pressure.
Trích dẫn luật: 2025 CA Building Code, Chapter 19 (Concrete)Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A slab-on-grade develops a network of random, map-like surface cracks within days of placement, but the cracks are shallow and do not reach the reinforcement. What is the MOST likely cause?
- After stripping the forms from a concrete wall, the contractor finds voids with exposed coarse aggregate and no paste in several areas near the base. This honeycombing was MOST likely caused by:
- A large slab pour is interrupted for 3 hours when the concrete supply is delayed. When placement resumes, a visible line forms where fresh concrete meets the partially set concrete. This cold joint is BEST prevented in future pours by:
- In a post-tensioned slab, the primary function of the tendons is to:
- A below-grade concrete basement wall shows persistent damp spots and mineral staining on the interior. The MOST effective long-term remedy is to:
- CALCULATION: A slab-on-grade measures 30 ft by 24 ft and is 5 inches thick. How many cubic yards of concrete are required, before adding waste?