During hot-weather concreting at 95 degrees F with dry wind, the MOST important immediate practice to prevent surface defects is to:
a.Increase the mix water to keep it workable
b.Protect the surface from moisture loss with fogging, evaporation retarder, or prompt curing
c.Use a higher-slump mix and delay finishing
d.Add extra retarder and leave it exposed
Giải thích
In hot, windy conditions rapid evaporation causes plastic shrinkage cracking, so the priority is reducing moisture loss with fogging, evaporation retarders, and prompt curing. Adding mix water raises the water-cement ratio and weakens the concrete; leaving it exposed worsens evaporation.
Trích dẫn luật: 2025 CA Building Code, Chapter 19 (Concrete)Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- CALCULATION: A continuous footing is 60 feet long, 20 inches wide, and 12 inches deep. Approximately how many cubic yards of concrete does it require?
- CALCULATION: A rectangular column is 18 in by 18 in in cross-section and 10 feet tall. Ignoring reinforcement, how many cubic yards of concrete does it contain?
- A concrete supplier delivers a load with a measured slump much higher than ordered. Before rejecting or accepting, the BEST assumption about the likely cause and its effect is:
- A driveway slab cracks in a fairly straight line directly over a buried utility trench that was backfilled. The MOST likely cause is:
- Control joints (contraction joints) are tooled or saw-cut into a slab primarily to:
- CALCULATION: Concrete costs $165 per cubic yard. A footing pour needs 100 cubic feet of concrete plus 8 percent for waste. What is the approximate concrete cost?