What does the NEC require regarding testing of emergency systems?
a.No testing once commissioned
b.Testing only every 10 years
c.Periodic testing on a scheduled basis under simulated or maximum load
d.Testing performed only by the utility
Giải thích
Section 700.3 requires emergency systems to be tested periodically on a schedule acceptable to the authority having jurisdiction to ensure they are maintained in proper operating condition, including a witnessed acceptance test at installation. Leaving a system untested after commissioning would violate this requirement.
Trích dẫn luật: 2023 NEC §700.3Luyện miễn phí toàn bộ 521 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- How must emergency illumination be arranged with respect to the failure of a single lighting element?
- Which loads are typically served by a legally required standby system?
- Transfer equipment for an optional standby system must do what regarding the normal and standby sources?
- What capacity must an emergency system power source have?
- A storage-battery emergency source must be capable of maintaining the total emergency load for what minimum time and voltage?
- A PV system disconnecting means must be installed how?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-10 Electrical Trade Examination · Quy trình kiểm tra