Planning & EstimatingCâu 77 / 100
Before starting many hardscape or grading projects, a contractor typically must obtain what from the local jurisdiction?
a.The required building or grading permit
b.A fertilizer license only
c.A seed certificate
d.A paint color approval
Giải thích
Grading, retaining walls over a set height, and other hardscape work usually require a permit and inspections from the local building or public works department. Permit review checks drainage, setbacks, and structural safety. Skipping required permits can lead to fines and forced removal.
Luyện miễn phí toàn bộ 100 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- When estimating a job, which cost category covers wages, taxes, and workers' compensation for crew hours?
- How many square feet are in a rectangular lawn that is 45 feet by 60 feet?
- A fertilizer is applied at 4 pounds per 1,000 square feet. How much is needed for 5,000 square feet?
- A sod order covers 2,700 square feet. Sod is sold in pieces covering 10 square feet each. Roughly how many pieces are needed, ignoring waste?
- On a landscape plan, a legend or symbol schedule is used to do what?
- A contractor marks up material and labor to cover office costs, insurance, and profit. This markup is commonly called what?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-27 Landscaping Trade Exam · Quy trình kiểm tra