Cấp nước & Phân phốiCâu 15 / 360
A branch serves fixtures totaling 8 WSFU. Design velocity should be kept at or below about 8 feet per second to limit erosion and noise. If a given pipe size carries the demand at 6 fps, and the next size down would run at 11 fps, which is the better selection and why?
a.The smaller pipe, because it is cheaper
b.Either pipe; velocity does not matter
c.The larger pipe at 6 fps, because 11 fps exceeds the recommended velocity limit
d.The smaller pipe, because higher velocity prevents scaling
Giải thích
Excessive velocity (11 fps) causes erosion, noise, and water hammer, so the larger pipe running at 6 fps is the correct choice for staying at or below roughly 8 fps. Cost and scale-prevention claims do not override the velocity limitation, and velocity always matters in sizing.
Trích dẫn luật: 2022 California Plumbing Code (CPC) §610.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A residence has a closed water supply system because the water meter contains a check valve and a pressure regulator. As the water heater heats water, pressure spikes dangerously. What does the code require to relieve this?
- Which of the following is an approved standard material for potable cold and hot water distribution piping inside a building?
- A double check valve assembly (DC) is being selected for a cross-connection. Which application is appropriate for a DC assembly?
- What is the fundamental purpose of cross-connection control in a potable water system?
- When sizing water piping using the fixture unit method, why is the total demand in gpm always less than the simple sum of every fixture's peak flow?
- A flushometer (flush valve) water closet is being served. Compared with a flush-tank water closet, what does the flushometer require from the water distribution design?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra