Lập kế hoạch & Dự toánCâu 284 / 360
You are planning the DWV rough-in test. Under the CPC, a water test of the drainage and vent system is applied so that no section is tested with less than how much head of water?
a.10 feet of head (except the top 10 feet of the system)
b.1 foot of head
c.50 feet of head
d.No head is required; a visual check is enough
Giải thích
CPC 712.0 water test requires the DWV system to be filled so that no section is tested with less than a 10-foot head of water, except for the top 10 feet of the system. This confirms the joints are watertight before concealment. Plan the test at the rough-in stage so any leaks are fixed before cover-up.
Trích dẫn luật: CPC 712.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A plan symbol showing a small circle with a bisecting line and the note "FD" most likely indicates what?
- The plan scale is 1/4 inch = 1 foot. A water line measures 5 inches on the drawing. What is the actual pipe length?
- When you coordinate plumbing rough-in with the framing crew, why is it important to review the structural drawings before drilling floor joists?
- In estimating pipe for a run, why do experienced estimators add a waste/scrap allowance to the measured length?
- On the plans a valve symbol drawn as two triangles meeting point-to-point (a bowtie) most commonly represents which device?
- A restaurant plan calls for eight identical mop-sink rough-ins. Each rough-in needs 1 P-trap, 1 trap adapter, and 2 drop-ear elbows. How many drop-ear elbows go on the takeoff?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra