Lập kế hoạch & Dự toánCâu 294 / 360
An estimator prices a job at 2 fixtures' rough-in per hour and there are 40 fixtures. If the labor rate is $60/hour, what is the estimated rough-in labor cost?
a.$600
b.$800
c.$1,200
d.$2,400
Giải thích
At 2 fixtures per hour, 40 fixtures take 20 hours; 20 hours × $60 = $1,200. Converting fixture counts to hours to dollars is the core of labor estimating. Keep production rates and labor rates separate so either can be adjusted without redoing the whole estimate.
Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- You must coordinate a 4-inch sanitary line and an HVAC duct that cross in a tight ceiling. What is the best planning step to resolve the conflict before installation?
- What does the term "top-out" refer to during the phases of a plumbing installation?
- On a plumbing plan you see three parallel lines each with a different break symbol: a single dash, a dash-dot, and a solid. What is the best way to know which system each represents?
- Why should you check which edition of the California Plumbing Code the local jurisdiction has adopted before finalizing a design?
- In a plumbing isometric drawing, pipes are drawn at what angle to represent the three dimensions on a flat sheet?
- When planning a trench for a building sewer, what does the CPC require regarding the bottom of the trench?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra