When planning the drainage layout, why must roof and storm drainage generally be kept separate from the sanitary drainage system?
a.Because storm water is warmer
b.Because the code requires storm drainage to be an independent system, not discharged into the sanitary sewer, unless specifically approved by the authority
c.Because storm pipe is always larger than 12 inches
d.Because sanitary pipe cannot be plastic
Giải thích
CPC 1101.0 and related sections require storm drainage to be conveyed by an independent system rather than combined with sanitary drainage, except where a combined system is specifically approved. Mixing them can overload the sanitary sewer and treatment system during rain. Planning separate systems on the drawings keeps the layout compliant.
Trích dẫn luật: CPC 1101.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- On a plumbing plan, what does a "point of connection" (POC) note typically identify?
- When must a plumbing permit generally be obtained relative to starting the work?
- A single-line water piping diagram on the plans is best described as what?
- A bid schedule shows the plumbing rough-in must be complete before the concrete slab is poured. What does this tell you about coordination?
- Under the CPC, what is the general purpose of requiring a permit and inspections for plumbing work?
- You are counting fixtures for a two-bathroom house: each bathroom has 1 water closet, 1 lavatory, and 1 shower, and the kitchen has 1 sink. How many fixtures go on the rough-in count?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra