The down payment and progress payment limits in §7159 are designed primarily to:
a.Protect the homeowner from paying for work not yet done
b.Increase the contractor's cash flow
c.Guarantee the contractor's profit
d.Reduce the CSLB's workload
Giải thích
The payment restrictions in B&P §7159 protect homeowners by ensuring they do not pay substantially ahead of the work actually completed, reducing loss if a contractor abandons the job.
Trích dẫn luật: B&P §7159Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Which of the following must appear near the buyer's signature line as a required caution in a home improvement contract?
- For a service and repair contract, the buyer must receive a fully completed copy:
- A contractor completes 40% of a $20,000 job. Under §7159, the maximum he may have collected by that point (excluding a lawful down payment) is generally:
- A home improvement contract must identify the parties. This means it must include:
- Even for an emergency repair that the homeowner requested, the three-day right to cancel:
- Which of the following is listed among the prohibited acts that constitute cause for disciplinary action in connection with home improvement contracts?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)