A 'force majeure' clause in a construction contract typically addresses:

a.The arbitration venue
b.The maximum profit a contractor may earn
c.How change orders are priced
d.Excusable delays caused by events beyond the parties' reasonable control, such as natural disasters

Giải thích

A force majeure clause allocates the risk of extraordinary events beyond the parties' reasonable control, such as natural disasters, severe weather, war, or government orders, typically by excusing or extending time for performance rather than treating the delay as a breach. It does not set profit caps, price change orders, or fix the arbitration venue; its function is to relieve a party from liability for delays caused by qualifying uncontrollable events.

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi