Tài chính doanh nghiệpCâu 1181 / 1605
A contractor's annual overhead is $75,000 and projected direct costs are $500,000. On a job with $20,000 direct cost, how much overhead should be allocated using the cost-based method?
a.$1,500
b.$4,000
c.$3,000
d.$2,000
Giải thích
Overhead rate = $75,000 / $500,000 = 15%. Overhead allocated to this job = $20,000 x 15% = $3,000. This is added to direct cost before applying profit.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A job priced at $9,600 carried a 20% markup on cost. What was the direct cost?
- Which markup on cost produces a 20% gross margin?
- A contractor sells a job for $60,000 that cost $45,000. What is the gross profit margin?
- A contractor bids a job with $15,000 direct cost, adds 18% overhead, then 12% profit on the subtotal. What is the total bid (rounded to the nearest dollar)?
- If a contractor's overhead is fixed at $10,000 per month and he completes 5 jobs that month, the average overhead absorbed per job is:
- On a balance sheet, which of the following is a CURRENT asset?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)