A site plan shows the invert elevation of a building sewer as 102.50 ft at the upstream end and 101.90 ft at the downstream end, with 48 ft of run between the two points. What is the slope of the sewer in inches per foot?
a.0.0125 in per ft
b.0.10 in per ft
c.0.125 in per ft
d.0.15 in per ft
Giải thích
The fall is 102.50 - 101.90 = 0.60 ft, which is 0.60 x 12 = 7.2 in, and 7.2 in divided by the 48 ft run gives 0.15 in per ft. The value 0.0125 is the slope expressed in feet per foot, not inches per foot, so it is off by a factor of 12. One tenth of an inch per foot would produce only 4.8 in of fall over 48 ft, and 0.125 in per ft, the familiar 1/8 in per ft grade, would produce 6 in of fall. Both are plausible-looking but leave the pipe higher than the plan calls for at the connection.
Luyện miễn phí toàn bộ 120 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A water distribution system that will operate at 45 psi working pressure is tested with water. The plumber pumps it to 48 psi, and after 15 minutes the gauge reads 46 psi. How should the result be reported?
- On a set of plumbing drawings, which view shows the vertical arrangement of the DWV piping, the floor-to-floor relationships and the order of the connections, drawn at an angle and generally not to scale?
- A floor plan is drawn at a scale of 1/4 in = 1 ft. A straight run of cold water piping measures 3-1/2 in on the drawing. What is the actual length of that run?
- A building sewer runs 62 ft from the building drain to the connection at the main and is to be graded at 1/4 in per foot. The invert elevation at the upstream end is 100.00 ft. What is the invert elevation at the downstream end?
- A crew is setting sewer pipe in a trench 5 ft 6 in deep with vertical walls cut in previously disturbed soil. No sloping, shoring or shielding has been installed. What does OSHA require before a worker enters?
- A trench 7 ft deep with a 3 ft wide bottom is excavated in Type C soil and will be protected by sloping the walls at 1-1/2 to 1. How wide must the excavation be at the top?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với Journeyman Plumber Licensing Exam (UPC/IPC-based) · Quy trình kiểm tra