Codes & SafetyCâu 110 / 120
On a set of plumbing drawings, which view shows the vertical arrangement of the DWV piping, the floor-to-floor relationships and the order of the connections, drawn at an angle and generally not to scale?
a.The riser or isometric diagram
b.The floor plan view
c.The civil or site utility plan
d.The fixture schedule
Giải thích
A riser or isometric diagram is a single-line pictorial drawing of the system in three dimensions; it shows what connects to what and at what level but is not drawn to scale, so lengths cannot be measured off it. The floor plan is a scaled overhead view used to locate piping horizontally and to read symbols such as CW, HW, waste and vent. The site plan shows the sewer and water service outside the building along with invert elevations and benchmarks. The fixture schedule is a table of fixture types, models and connection sizes, not a view of the piping.
Luyện miễn phí toàn bộ 120 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A high-rise DWV system is water tested in sections. The highest joint in the section currently under test is 28 ft above the building drain, and three more floors of piping continue above that section. To what height above the building drain must the test standpipe extend?
- Freezing weather makes a water test impractical, so the DWV rough-in is air tested instead. Which combination of test pressure and duration satisfies the code?
- A water distribution system that will operate at 45 psi working pressure is tested with water. The plumber pumps it to 48 psi, and after 15 minutes the gauge reads 46 psi. How should the result be reported?
- A floor plan is drawn at a scale of 1/4 in = 1 ft. A straight run of cold water piping measures 3-1/2 in on the drawing. What is the actual length of that run?
- A site plan shows the invert elevation of a building sewer as 102.50 ft at the upstream end and 101.90 ft at the downstream end, with 48 ft of run between the two points. What is the slope of the sewer in inches per foot?
- A building sewer runs 62 ft from the building drain to the connection at the main and is to be graded at 1/4 in per foot. The invert elevation at the upstream end is 100.00 ft. What is the invert elevation at the downstream end?