Business FinancesQuestion 300 of 690
A contractor's direct job costs are $70,000. The overhead rate is 15% of direct costs, and the contractor wants a 10% profit on the total of direct costs plus overhead. What is the bid price?
a.$80,500
b.$87,500
c.$84,000
d.$88,550
Explanation
Direct costs $70,000 × 1.15 = $80,500 (costs plus overhead). $80,500 × 1.10 = $88,550 (adding profit). Overhead is applied first, then profit on the loaded cost.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor wants a 20% gross margin on the SELLING price. If the job costs $48,000, what must the selling price be?
- A contractor applies a 25% markup on cost. Expressed as a margin on the selling price, this 25% markup equals approximately:
- A contractor's annual overhead is $120,000 and the company expects $600,000 in direct job costs for the year. What overhead rate, as a percentage of direct costs, should be applied to each job?
- A contractor buys a work truck for $45,000, expects to use it for 5 years, and estimates a salvage value of $5,000. Using straight-line depreciation, what is the annual depreciation expense?
- Depreciation of construction equipment is best described as:
- A contractor's quick (acid-test) view of liquidity differs from the current ratio mainly because the quick ratio:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review