Business FinancesQuestion 326 of 690
A worker is paid a base wage of $30 per hour. With a labor burden of 35%, what is the fully burdened hourly cost the contractor should use for estimating?
a.$10.50
b.$40.50
c.$30.00
d.$45.00
Explanation
Burdened cost = Base Wage × (1 + Burden Rate) = $30 × 1.35 = $40.50. Estimating with only the base wage would understate the true cost of labor.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor's job estimate includes $40,000 materials, $35,000 labor, and $25,000 subcontractors. The contractor adds 16% overhead and then 12% profit on the overhead-loaded cost. What is the bid price (rounded to the nearest dollar)?
- A contractor pays a worker $25 per hour for 45 hours in one week, with overtime at 1.5 times the regular rate for hours over 40. What are the gross wages for the week?
- Beyond an employee's gross wages, a contractor must also budget for the employer's share of payroll taxes. This additional cost is commonly referred to as:
- A contractor wins a job for $300,000 and incurs total costs of $264,000. What is the profit margin on the selling price?
- A contractor wants to keep a cash reserve equal to 2 months of fixed overhead. If monthly fixed overhead is $14,000, how large should the reserve be?
- Accounts payable on a contractor's balance sheet represents:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review