Contracts & ExecutionQuestion 537 of 1632

A prime contractor receives a $200,000 progress payment from the owner. The subcontract calls for $40,000 to a plumbing sub for completed work that was approved in the payment. Under B&P §7108.5, the prime must pay the sub within how many days of receipt?

a.Within 10 days of receiving each progress payment from the owner
b.Within 30 days of receiving each progress payment from the owner
c.Within 45 days of receiving each progress payment from the owner
d.Within 7 days of receiving each progress payment from the owner

Explanation

B&P §7108.5(a) gives the direct contractor 7 days after receipt of each progress payment to pay each subcontractor its share, unless the parties agree otherwise in writing; wrongful withholding costs 2 percent of the amount due per month plus the prevailing party's attorney's fees (§7108.5(b)-(c)), and in a good faith dispute no more than 150 percent of the disputed amount may be held back. Each wrong number is a real California deadline for a DIFFERENT payment. (a) 10 days is Civil Code §8814, the direct contractor's deadline to pass RETENTION through to subs. (b) 30 days is Civil Code §8800, the owner's deadline to pay the direct contractor a progress payment after a demand. (c) 45 days is Civil Code §8812, the owner's deadline to release retention after completion of the work of improvement.

Law Reference: Bus. & Prof. Code §7108.5; cf. Civil Code §8800, §8812, §8814

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report