A prime contractor receives a $200,000 progress payment from the owner. The subcontract calls for $40,000 to a plumbing sub for completed work that was approved in the payment. Under B&P §7108.5, the prime must pay the sub within how many days of receipt?
Explanation
B&P §7108.5(a) gives the direct contractor 7 days after receipt of each progress payment to pay each subcontractor its share, unless the parties agree otherwise in writing; wrongful withholding costs 2 percent of the amount due per month plus the prevailing party's attorney's fees (§7108.5(b)-(c)), and in a good faith dispute no more than 150 percent of the disputed amount may be held back. Each wrong number is a real California deadline for a DIFFERENT payment. (a) 10 days is Civil Code §8814, the direct contractor's deadline to pass RETENTION through to subs. (b) 30 days is Civil Code §8800, the owner's deadline to pay the direct contractor a progress payment after a demand. (c) 45 days is Civil Code §8812, the owner's deadline to release retention after completion of the work of improvement.
Law Reference: Bus. & Prof. Code §7108.5; cf. Civil Code §8800, §8812, §8814This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- Work on a private project ceases for 35 continuous days due to a financing dispute. The owner records a Notice of Cessation under Civil Code §8174. What is the effect on subcontractor lien deadlines?
- A consumer home-improvement contract includes a clause forcing the homeowner to pay all of the contractor's attorney fees in any dispute, while barring the homeowner from recovering her own. Under Civil Code §1670.5, a court reviewing this provision may:
- A general contractor receives a joint check made payable to BOTH the subcontractor and its material supplier. Best practice in California is for the GC to:
- A subcontractor on a private project completes its work and the prime contractor withholds 5% retention. The owner has accepted the project and released all retention to the prime. Under Civil Code §8814, the prime must release the sub's retention within how many days?
- A home-improvement contract has a total contract price of $48,000. Under B&P §7159(d), the MAXIMUM down payment the contractor may demand or accept before any work or material delivery is:
- A consumer signs a home-solicitation contract for solar panel installation at her residence on a Tuesday at 6 PM. Under Civil Code §1689.5 et seq., she may cancel without penalty until midnight on:
Last reviewed: · editorial process