Contracts & ExecutionQuestion 539 of 690
A home-improvement contract has a total contract price of $48,000. Under B&P §7159(d), the MAXIMUM down payment the contractor may demand or accept before any work or material delivery is:
a.$2,500
b.$1,000
c.$4,800 (10% of contract)
d.$5,000 or 10%, whichever is greater
Explanation
B&P §7159(d) caps the down payment on a home improvement contract at the LESSER of $1,000 or 10% of the contract price, exclusive of finance charges. Here 10% would be $4,800 so the lesser amount of $1,000 controls.
Law Reference: Bus. & Prof. Code §7159(d)Practice all 690 questions free — no signup required.
Related questions on this topic
- A general contractor receives a joint check made payable to BOTH the subcontractor and its material supplier. Best practice in California is for the GC to:
- A prime contractor receives a $200,000 progress payment from the owner. The subcontract calls for $40,000 to a plumbing sub for completed work that was approved in the payment. Under B&P §7108.5, the prime must pay the sub within how many days of receipt?
- A subcontractor on a private project completes its work and the prime contractor withholds 10% retention. The owner has accepted the project and released all retention to the prime. Under B&P §7107, the prime must release the sub's retention within how many days?
- A consumer signs a home-solicitation contract for solar panel installation at her residence on a Tuesday at 6 PM. Under Civil Code §1689.5 et seq., she may cancel without penalty until midnight on:
- A contractor wishes to collect progress payments on a home-improvement contract. Under B&P §7159.5, each progress payment must:
- A commercial construction contract has a liquidated damages clause of $2,500 per day for late completion. Under Civil Code §1671(b), this clause is presumed:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review