Contracts & ExecutionQuestion 535 of 690
A consumer home-improvement contract includes a clause forcing the homeowner to pay all of the contractor's attorney fees in any dispute, while barring the homeowner from recovering her own. Under Civil Code §1670.5, a court reviewing this provision may:
a.Enforce the clause because both parties signed
b.Refuse to enforce the clause, limit its application, or strike it as unconscionable
c.Award triple damages to the homeowner automatically
d.Refer the matter to the CSLB for mandatory arbitration
Explanation
Civil Code §1670.5 authorizes a court to refuse enforcement of an unconscionable contract or any unconscionable clause, or to limit its application, to avoid an unconscionable result. One-sided fee-shifting in a consumer contract is a classic example.
Law Reference: Civ. Code §1670.5Practice all 690 questions free — no signup required.
Related questions on this topic
- On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
- A drywall subcontractor on a private works project finished its scope on March 1. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
- Work on a private project ceases for 35 continuous days due to a financing dispute. The owner records a Notice of Cessation under Civil Code §8174. What is the effect on subcontractor lien deadlines?
- A general contractor receives a joint check made payable to BOTH the subcontractor and its material supplier. Best practice in California is for the GC to:
- A prime contractor receives a $200,000 progress payment from the owner. The subcontract calls for $40,000 to a plumbing sub for completed work that was approved in the payment. Under B&P §7108.5, the prime must pay the sub within how many days of receipt?
- A subcontractor on a private project completes its work and the prime contractor withholds 10% retention. The owner has accepted the project and released all retention to the prime. Under B&P §7107, the prime must release the sub's retention within how many days?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review