Contracts & ExecutionQuestion 532 of 1632

On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?

a.30 days
b.60 days
c.90 days
d.120 days

Explanation

Under Civil Code §8412, a direct contractor has 60 days after recording of a Notice of Completion or Notice of Cessation to record a mechanics lien. Without such a notice, the period is 90 days after actual completion.

Law Reference: Civ. Code §8412

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report