A homeowner verbally asks the contractor to upgrade tile during a bathroom remodel. The contractor proceeds without a written change order. Under B&P §7159, the contractor's ability to collect the extra $3,200 is:
Explanation
B&P §7159(c)(5) makes a change-order form part of the contract only if it is in writing and signed by the parties before the work covered by it starts, and the opening words of §7159(d) say the same of the contract and any changes to it — so an unsigned verbal upgrade leaves the extra at risk. A daily log is the contractor's own record, not the owner's signature. No dollar figure turns a verbal change order into an enforceable one; there is no $5,000 line in §7159. And the risk is not the complaint: the money is at risk in a collection action whether or not the homeowner ever contacts the CSLB.
Law Reference: B&P Code §7159(c)(5); §7159(d)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A contractor's job-cost report shows materials are 15% over budget while labor is on budget at the 50% completion point. The contractor should:
- A subcontractor signs a CONDITIONAL waiver and release on progress payment under Civil Code §8132 in exchange for a check that later bounces. What is the legal effect on the waiver?
- A prime contractor's subcontract requires the subcontractor to indemnify the prime for ALL claims, including those arising from the prime's SOLE negligence. Under Civil Code §2782, this broad-form indemnity provision is:
- An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?
- On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
- A drywall subcontractor on a private works project finished its scope on March 1, the same day the work of improvement was actually completed. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
Last reviewed: · editorial process