Contracts & ExecutionQuestion 530 of 690
A homeowner verbally asks the contractor to upgrade tile during a bathroom remodel. The contractor proceeds without a written change order. Under B&P §7159(j), the contractor's ability to collect the extra $3,200 is:
a.At risk because every change order must be in writing, signed by both parties, and attached to the contract
b.Guaranteed if the contractor documents the change in a daily log
c.Guaranteed because verbal change orders are valid up to $5,000
d.At risk only if the homeowner files a CSLB complaint
Explanation
Under B&P §7159(j), any change to a home improvement contract must be in writing, signed by both the contractor and the owner, and incorporated into the contract. Verbal change orders are unenforceable as home improvement contract modifications.
Law Reference: Bus. & Prof. Code §7159(j)Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor's job-cost report shows materials are 15% over budget while labor is on budget at the 50% completion point. The contractor should:
- A subcontractor signs a CONDITIONAL waiver and release on progress payment under Civil Code §8132 in exchange for a check that later bounces. What is the legal effect on the waiver?
- A prime contractor's subcontract requires the subcontractor to indemnify the prime for ALL claims, including those arising from the prime's SOLE negligence. Under Civil Code §2782, this broad-form indemnity provision is:
- An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?
- On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
- A drywall subcontractor on a private works project finished its scope on March 1. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review