An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?
Explanation
Civil Code §8182 lets an owner record a notice of completion on or within 15 days after completion, so a notice recorded on day 12 is valid - as the stem says it is. What it does is set by §8412: a direct contractor must record its lien before the EARLIER of 90 days after completion or 60 days after the owner records the notice, so once the notice is on record the 60-day clock governs, because it runs out first. The 90-day period is real but measured from completion, not from the recording. The 30-day window is real too, but §8414 gives it to claimants other than the direct contractor - subcontractors and suppliers. And a notice of completion shortens a deadline; it never extinguishes the lien right.
Law Reference: Civil Code §8182; §8412; §8414This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A subcontractor signs a CONDITIONAL waiver and release on progress payment under Civil Code §8132 in exchange for a check that later bounces. What is the legal effect on the waiver?
- A prime contractor's subcontract requires the subcontractor to indemnify the prime for ALL claims, including those arising from the prime's SOLE negligence. Under Civil Code §2782, this broad-form indemnity provision is:
- A homeowner verbally asks the contractor to upgrade tile during a bathroom remodel. The contractor proceeds without a written change order. Under B&P §7159, the contractor's ability to collect the extra $3,200 is:
- On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
- A drywall subcontractor on a private works project finished its scope on March 1, the same day the work of improvement was actually completed. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
- Work on a private project ceases for 35 continuous days due to a financing dispute. The owner records a Notice of Cessation under Civil Code §8174. What is the effect on subcontractor lien deadlines?
Last reviewed: · editorial process