Contracts & ExecutionQuestion 531 of 1605

An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?

a.Direct contractors have 90 days from the recording of the Notice of Completion
b.Direct contractors lose all lien rights immediately upon recording
c.Direct contractors have 30 days because the Notice was not recorded within 15 days
d.The Notice of Completion is invalid because it must be recorded within 15 days after actual completion

Explanation

Under Civil Code §8182, a Notice of Completion must be recorded within 15 days after actual completion. A Notice recorded after the 15-day window has no effect on shortening lien deadlines, so the standard 90-day-from-completion deadline applies.

Law Reference: Civ. Code §8182

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report