A drywall subcontractor on a private works project finished its scope on March 1, the same day the work of improvement was actually completed. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
Explanation
Civil Code §8414 gives a claimant other than the direct contractor until the earlier of 90 days after completion of the work of improvement or 30 days after the owner records a notice of completion or cessation. No notice was recorded here, so the 90-day limb controls and the lien must be recorded by about May 30. The 30-day figure is the shortened deadline that only a recorded notice triggers, and it runs from that recordation rather than from the subcontractor's last day. Sixty days is the direct contractor's post-notice window under §8412, not a subcontractor's. No deadline in the California lien statute runs 180 days.
Law Reference: Civil Code §8414; cf. §8412This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A homeowner verbally asks the contractor to upgrade tile during a bathroom remodel. The contractor proceeds without a written change order. Under B&P §7159, the contractor's ability to collect the extra $3,200 is:
- An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?
- On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
- Work on a private project ceases for 35 continuous days due to a financing dispute. The owner records a Notice of Cessation under Civil Code §8174. What is the effect on subcontractor lien deadlines?
- A consumer home-improvement contract includes a clause forcing the homeowner to pay all of the contractor's attorney fees in any dispute, while barring the homeowner from recovering her own. Under Civil Code §1670.5, a court reviewing this provision may:
- A general contractor receives a joint check made payable to BOTH the subcontractor and its material supplier. Best practice in California is for the GC to:
Last reviewed: · editorial process