Contracts & ExecutionQuestion 533 of 690
A drywall subcontractor on a private works project finished its scope on March 1. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
a.March 31 (30 days after its own completion)
b.April 30 (60 days after its own completion)
c.May 30 (90 days after actual completion of the project)
d.August 29 (180 days after its own completion)
Explanation
Under Civil Code §8414, when no Notice of Completion or Cessation is recorded, a non-direct claimant (subcontractor or supplier) has 90 days after actual completion of the work of improvement to record its lien. If a notice were recorded, the period would shorten to 30 days for subcontractors.
Law Reference: Civ. Code §8414Practice all 690 questions free — no signup required.
Related questions on this topic
- A homeowner verbally asks the contractor to upgrade tile during a bathroom remodel. The contractor proceeds without a written change order. Under B&P §7159(j), the contractor's ability to collect the extra $3,200 is:
- An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?
- On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
- Work on a private project ceases for 35 continuous days due to a financing dispute. The owner records a Notice of Cessation under Civil Code §8174. What is the effect on subcontractor lien deadlines?
- A consumer home-improvement contract includes a clause forcing the homeowner to pay all of the contractor's attorney fees in any dispute, while barring the homeowner from recovering her own. Under Civil Code §1670.5, a court reviewing this provision may:
- A general contractor receives a joint check made payable to BOTH the subcontractor and its material supplier. Best practice in California is for the GC to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review