Contracts & ExecutionQuestion 533 of 690

A drywall subcontractor on a private works project finished its scope on March 1. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:

a.March 31 (30 days after its own completion)
b.April 30 (60 days after its own completion)
c.May 30 (90 days after actual completion of the project)
d.August 29 (180 days after its own completion)

Explanation

Under Civil Code §8414, when no Notice of Completion or Cessation is recorded, a non-direct claimant (subcontractor or supplier) has 90 days after actual completion of the work of improvement to record its lien. If a notice were recorded, the period would shorten to 30 days for subcontractors.

Law Reference: Civ. Code §8414

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report