SafetyQuestion 95 of 1632

Which type of scaffolding requires specific training before workers can erect, disassemble, or use it?

a.Only scaffolding over 10 feet high
b.All scaffolding, regardless of height
c.Only tube-and-coupler scaffolding
d.Only the workers who erect and dismantle it

Explanation

Neither the Construction Safety Orders nor the federal standard puts a height or a type limit on scaffold training: section 1637(k)(1) requires erection and dismantling to be performed under the supervision and direction of a qualified person whatever the scaffold, and 29 CFR 1926.454(a) requires each employee who performs work WHILE ON a scaffold to be trained by a person qualified in the subject matter. The three wrong answers each import a limit from somewhere else. Ten feet (a) is the federal trigger for fall protection on a supported scaffold, not for training. Tube-and-coupler scaffolds (c) do carry extra design duties, which is why the type feels special. And (d) is the commonest misconception of the four: training belongs to the people who stand on the platform as much as to the crew that builds it, because the hazards they meet - overloading, missing planks, guardrails removed for a delivery - come after erection.

Law Reference: 8 CCR §1637(k)(1); §1510(a); 29 CFR 1926.454(a)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report