Insurance & LiensQuestion 1572 of 1605

A claim on a private-project payment bond generally requires the claimant to have:

a.Posted a 125% bond
b.Given the preliminary notice required for lien rights (unless excused), because bond rights parallel lien rights
c.Recorded a mechanics lien first
d.Obtained a court judgment first

Explanation

Under Civil Code §8600 et seq., a claimant's right to recover on a private-project payment bond generally depends on having given the preliminary notice required to preserve lien rights (unless excused, e.g., laborers). The bond claim parallels the lien claim's notice conditions.

Law Reference: Civ. Code §8600

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report