A notice of completion was recorded on July 1. An unpaid drywall subcontractor wants to record a mechanics lien. The last day to record is approximately:

a.July 5
b.August 30 (60 days)
c.September 29 (90 days)
d.July 31 (30 days)

Explanation

Under Civil Code §8414, once a notice of completion is recorded, a claimant other than the direct contractor must record within 30 days. Counting 30 days from July 1 lands at the end of July. Only the direct contractor would get 60 days.

Law Reference: Civ. Code §8414

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report