Insurance & LiensQuestion 1535 of 1632

A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:

a.Triggering 30 days for other claimants and 60 days for the direct contractor
b.Triggering 60 days for other claimants and 90 days for the direct contractor
c.Leaving every claimant with 90 days from actual completion of the work
d.Extending each claimant's deadline to one year from the recording date

Explanation

A recorded notice of cessation has the same effect as a notice of completion: Civil Code §8414 cuts claimants other than the direct contractor to 30 days after recording, and §8412 gives the direct contractor 60 days. (b) swaps the two figures, and reversing them is the most common error on this pair. (c) is the rule when nothing is recorded — 90 days after completion for everyone — and is exactly what the recording is meant to shorten. (d) confuses this with the §8460 outer limit for bringing a foreclosure action after a lien is recorded.

Law Reference: Civil Code §8412 / §8414

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report