A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:

a.Triggering the shorter deadlines: 30 days for other claimants and 60 days for the direct contractor
b.Having no effect on deadlines
c.Eliminating the direct contractor's lien rights
d.Extending all deadlines to one year

Explanation

A recorded notice of cessation (like a notice of completion) triggers the shorter statutory deadlines under Civil Code §8414: 30 days for claimants other than the direct contractor, and 60 days for the direct contractor. Without it, all have 90 days from completion.

Law Reference: Civ. Code §8414