Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?

a.The subcontractor
b.The material supplier
c.The surety company
d.The project owner

Explanation

On a performance bond, the obligee is the party protected by the guarantee of completion — typically the project owner. The contractor is the principal and the bonding company is the surety. Subs and suppliers are protected instead by the payment bond.