Insurance & LiensQuestion 1559 of 1605

A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:

a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)
d.April 30 (60 days)

Explanation

With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.

Law Reference: Civ. Code §8412

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report