Insurance & LiensQuestion 1559 of 163277% of test-takers answer this correctly

A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:

a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)
d.April 30 (60 days)

Explanation

With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.

Law Reference: Civ. Code §8412

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report