A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)
d.April 30 (60 days)
Explanation
With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.
Law Reference: Civ. Code §8412Practice all 1605 questions free — no signup required.
Related questions on this topic
- On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
- After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
- 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
- Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
- Which best describes the difference between the payment bond and the performance bond on the SAME project?
- A mechanics lien on a private project should describe the property with:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)