Contracts & ExecutionQuestion 738 of 1605

To cancel within the three-day period, the buyer must:

a.Get the contractor's written permission
b.Appear in person at the CSLB office
c.Wait until work is 50% complete
d.Send or deliver written notice of cancellation by midnight of the third business day

Explanation

The buyer exercises the right to cancel by giving written notice (for example, mailing the cancellation form) by midnight of the third business day after signing.

Law Reference: Civil Code §1689.7