Contracts & ExecutionQuestion 740 of 1605

For a service and repair contract, the buyer must receive a fully completed copy:

a.Never; it is optional
b.Before any work commences
c.Only after payment
d.Within 30 days of completion

Explanation

As with home improvement contracts, B&P §7159.10 requires the contractor to give the buyer a completed copy of the service and repair contract before work begins.

Law Reference: B&P §7159.10