Contracts & ExecutionQuestion 740 of 1605
For a service and repair contract, the buyer must receive a fully completed copy:
a.Never; it is optional
b.Before any work commences
c.Only after payment
d.Within 30 days of completion
Explanation
As with home improvement contracts, B&P §7159.10 requires the contractor to give the buyer a completed copy of the service and repair contract before work begins.
Law Reference: B&P §7159.10Practice all 1605 questions free — no signup required.
Related questions on this topic
- If a home improvement contract fails to contain the elements required by §7159, the contractor may be subject to:
- To cancel within the three-day period, the buyer must:
- Which of the following must appear near the buyer's signature line as a required caution in a home improvement contract?
- A contractor completes 40% of a $20,000 job. Under §7159, the maximum he may have collected by that point (excluding a lawful down payment) is generally:
- The down payment and progress payment limits in §7159 are designed primarily to:
- A home improvement contract must identify the parties. This means it must include:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)