Contracts & ExecutionQuestion 739 of 1605

Which of the following must appear near the buyer's signature line as a required caution in a home improvement contract?

a.A notice that the buyer is entitled to a completely filled-in copy of the contract before work begins
b.A statement that the buyer waives all rights
c.The contractor's blood type
d.The name of the salesperson's supervisor only

Explanation

B&P §7159 requires notice language ensuring the buyer receives a fully completed copy of the signed contract before work begins and understands their rights, including the right to cancel.

Law Reference: B&P §7159(c)

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)