Contracts & ExecutionQuestion 757 of 1605

A homeowner insists on paying the full $30,000 up front to 'lock in the price.' The contractor should know that accepting this:

a.Is required to reserve materials
b.Is required if the owner offers
c.Would violate the down payment limit and payment-for-work-performed rules absent a joint control
d.Is fine because the owner volunteered

Explanation

Even if the owner offers, B&P §7159 prohibits accepting a down payment over $1,000 (or 10%) and payments exceeding the value of work performed, unless funds are held by an approved joint control.

Law Reference: B&P §7159(d)

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report