Contracts & ExecutionQuestion 759 of 1605

A contractor performing a $700 service and repair job collects a $150 deposit before starting. This is:

a.Allowed because it is under 25%
b.Allowed because it is under $200
c.Allowed because the buyer requested the work
d.Not allowed, because no payment may be collected until the service and repair work is complete

Explanation

B&P §7159.10 prohibits collecting any payment on a service and repair contract until the work is finished; a pre-start deposit is not permitted.

Law Reference: B&P §7159.10