Contracts & ExecutionQuestion 758 of 1605

Which is a required feature of the progress payment schedule in a home improvement contract?

a.It may be left to the contractor's later discretion
b.Each payment amount must be stated and tied to a described phase of work
c.It may only be expressed as a single lump sum due at start
d.It must be paid entirely at signing

Explanation

B&P §7159 requires the schedule of progress payments to state each payment's dollar amount and correlate it to a specifically described phase of the work.

Law Reference: B&P §7159