Business FinancesQuestion 1200 of 1605

A contractor bills $75,000 on a job. The contract requires 10% retention and the owner also back-charges $1,500 for a utility relocation. How much will the contractor receive on this billing?

a.$73,500
b.$66,000
c.$67,500
d.$65,000

Explanation

Retention = 10% of $75,000 = $7,500. After retention: $75,000 - $7,500 = $67,500. Then subtract the $1,500 back-charge: $67,500 - $1,500 = $66,000.