Business FinancesQuestion 1212 of 1632

A contractor completes a $180,000 contract billed with 5% retention. Two-thirds of the way through he has billed $120,000. How much retention is being held at that point?

a.$9,000
b.$114,000
c.$12,000
d.$6,000

Explanation

Retention held to date = 5% of the amount billed to date = 5% x $120,000 = $6,000 (d); it accrues on each progress billing until released at completion. Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026. (a) $9,000 applies the correct 5% to the full $180,000 contract instead of the $120,000 billed. (c) $12,000 is 10% of the billed amount, the pre-2026 private-works custom. (b) $114,000 is the amount paid out, not the amount held.

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report