A contractor charges $85/hour to the customer for labor that costs him $52/hour fully burdened. What is the gross margin on labor?

a.33%
b.38.8%
c.52%
d.63.5%

Explanation

Gross profit per hour = $85 - $52 = $33. Margin = $33 / $85 = 0.388 = 38.8%. (Markup on cost would be $33 / $52 = 63.5%.)