Chapter 5 of 615% of exam

Construction Engineering and Management

Construction engineering covers planning, scheduling, cost control, and earthwork for building projects. The exam tests CPM scheduling, earned-value metrics, quantity take-offs, and temporary works.

Scheduling with CPM

The critical path method computes early and late start/finish times. Total float = Late Finish - Early Finish is the slack an activity has without delaying the project; critical-path activities have zero float. The critical path sets the shortest possible project duration.

Earned Value and Cost Control

Earned-value management compares planned, earned, and actual costs. The Cost Performance Index CPI = EV/AC and Schedule Performance Index SPI = EV/PV flag problems: values below 1.0 mean over budget or behind schedule, respectively.

Earthwork and Quantities

Excavated soil swells, so loose volume = bank volume x (1 + swell); compacted fill shrinks. Concrete quantities convert from cubic feet to cubic yards by dividing by 27. Accurate take-offs drive ordering, hauling, and cost estimates.