What is the PRINCE2 7 Foundation Practice Exam exam like?+
About 60 questions, 60 minutes, and you need 36/60 (60%)% to pass. Practice by topic here, then take the full timed mock exam to gauge readiness.
Are these the real exam questions?+
No. Every question is 100% original, written from public primary sources with explanations. We never copy real exam questions or paid prep material.
Can I study in Chinese or Spanish?+
PrepPass practice is in English, 中文 and Español. The official exam is in English — switch the question language to English any time to rehearse the exact terminology you'll see on test day.
Sample practice questions
A few real questions from this free bank, with full explanations. Use the practice tool above for the whole set.
- 1. The Seven Principles
How many principles does PRINCE2 7 define, and what is their defining characteristic?
- a.Five principles that may be adopted selectively depending on project size
- b.Seven principles that apply only to large, high-risk projects
- c.Seven principles that must all be applied for a project to be genuinely following PRINCE2
- d.Nine principles that replace the need for a business case
Answer: c
Explanation: PRINCE2 7 has seven principles, and they are universal: unless all seven are applied, the project is not being managed with PRINCE2. They are not optional or scaled by project size.
- 2. The Seven Principles
Under the 'manage by exception' principle, what should a manager do while a plan is forecast to stay within its agreed tolerances?
- a.Continue without escalating, as the delegated level of management has authority to proceed
- b.Escalate to the next level of management for approval before any further work
- c.Halt the work until the Project Board reviews progress
- d.Reduce all tolerances to zero to keep tight control
Answer: a
Explanation: Manage by exception sets tolerances for each objective and delegates day-to-day authority. As long as work is forecast to stay within tolerance, the lower level proceeds; only a forecast breach is escalated as an exception.
- 3. The Seven Principles
When should lessons be sought and acted upon under the 'learn from experience' principle?
- a.Only at project closure, when an end project report is written
- b.Throughout the project: lessons are sought at the start, recorded during, and passed on at the end
- c.Only when a serious problem or exception occurs
- d.Only during the initiation stage, before the plans are baselined
Answer: b
Explanation: Learn from experience is continuous. Teams look for relevant lessons when starting, capture new lessons as the project runs, and pass lessons on when it closes so future projects benefit.
- 4. The Seven Practices
Which PRINCE2 practice is concerned with whether the project remains desirable, viable and achievable?
- a.Business case
- b.Progress
- c.Quality
- d.Organizing
Answer: a
Explanation: The business case practice develops and maintains the justification, testing that the project is desirable (benefits vs. cost/risk), viable (deliverable) and achievable (benefits realisable) across its life.
- 5. The Seven Practices
The theme formerly called 'Change' is now covered by which PRINCE2 7 practice?
- a.Plans
- b.Issues
- c.Quality
- d.Business case
Answer: b
Explanation: In PRINCE2 7 the 'Issues' practice handles requests for change, off-specifications and problems/concerns, controlled through issue and change control procedures rather than a separate 'Change' theme.
- 6. The Seven Processes
Which process is owned by the Project Board and provides overall direction and key authorisation decisions?
- a.Managing a stage boundary
- b.Controlling a stage
- c.Initiating a project
- d.Directing a project
Answer: d
Explanation: Directing a project is the Project Board's process. Through it the board authorises initiation, the project, each stage, and closure, and gives ad hoc direction, without being involved in day-to-day management.
- 7. The Seven Processes
Which process is used by a Team Manager to accept, execute and deliver the work packages that create the project's products?
- a.Controlling a stage
- b.Managing a stage boundary
- c.Managing product delivery
- d.Directing a project
Answer: c
Explanation: Managing product delivery is the interface where a Team Manager agrees a work package, oversees its execution, and delivers completed products back to the Project Manager for review and approval.
- 8. Management Products & Tailoring
PRINCE2 groups management products into which three types?
- a.Mandates, briefs and charters
- b.Baselines, records and reports
- c.Plans, risks and issues
- d.Inputs, processes and outputs
Answer: b
Explanation: Management products are of three kinds: baselines (defining products such as the PID and Business Case), records (dynamic logs such as the risk and issue registers), and reports (communicating status, such as the highlight report).
- 9. Management Products & Tailoring
What does the principle 'tailor to suit the project' require a team to consider?
- a.Removing any principles that seem inconvenient for the project
- b.Applying the method identically on every project for consistency
- c.Adapting the method to the project's context, such as its scale, complexity and risk
- d.Delegating all tailoring decisions to the supplier organisation
Answer: c
Explanation: Tailoring adapts PRINCE2 to the environment, size, complexity, importance, team capability and risk of the project, while still applying all seven principles. It is not an excuse to drop principles.
- 10. Roles & Governance
Which three roles make up the Project Board?
- a.Project Manager, Team Manager and Project Support
- b.Executive, Senior User and Senior Supplier
- c.Executive, Project Manager and Project Assurance
- d.Senior User, Change Authority and Team Manager
Answer: b
Explanation: The Project Board comprises the Executive (business interests), the Senior User (user interests and benefits) and the Senior Supplier (supplier/technical interests), together representing the three primary stakeholder interests.