Operational ProceduresPregunta 75 de 100

In a formal change-management process, what should be prepared in case a change causes unexpected problems in production?

a.A louder alarm
b.A rollback (back-out) plan
c.A brighter display
d.A faster CPU

Explicación

A rollback or back-out plan defines how to revert a change safely if it fails, minimizing downtime. It is a core part of responsible change management and unrelated to hardware upgrades or alarms.