Examen CSLB de Leyes y NegociosExamen de Licencia de Contratista de California (CSLB) — Práctica de Leyes y Negocios
- 1,632 free practice questions, every one explained · no signup
- Full-length timed mock exam, same length as the real one — free
- Free online chapters · Study guide book (PDF + EPUB): $24.99 one-time
- Languages: English · 中文, Español, Tiếng Việt (690 of 1,632 questions translated)
CSLB Law and Business Examination — 115 preguntas — 5 proveedores de preparación independientes coinciden; CSLB no publica ninguna. · 210 minutos · Puntuación para aprobar: No publicado por CSLB. Datos completos y fuentes · Written from: California Contractors State License Board (CSLB) · Last updated: September 2026
Prueba 10 preguntas del CSLB — unos 5 minutos
Cada respuesta explicada, y ves cómo lo enseña la guía de estudio. Gratis, sin registro.

¿Examen en menos de dos semanas?
Una hoja de referencia a color e imprimible: el formato, las áreas de contenido y las cifras clave, cada una comprobada con una fuente con nombre y fecha.
4 páginas · US Letter · PDF imprimible · tuyo para siempre
El examen de Leyes y Negocios del CSLB (Contractors State License Board) es obligatorio para obtener una licencia de contratista en California: todo solicitante lo rinde salvo que CSLB otorgue una exención.
Última revisión: · proceso editorial
Empieza aquí — tu ruta de estudio gratis
Todo lo que necesitas para aprobar el examen CSLB de Derecho y Negocios, en orden — mira, lee y practica.
- 1Mira el curso en videoNuevo · semanalLecciones completas tipo clase para las 7 secciones. La lección 1 ya está disponible.
- 2Lee la guía de estudio — gratis en líneaLos 7 capítulos, conforme a la ley 2026. El núcleo de cada capítulo — las reglas y cómo se aplican — es gratis en línea; los capítulos completos, con los catálogos y la hoja de cifras clave de cada uno, están en el eBook (PDF + EPUB) por $24.99.
- 3Practica preguntas + simulacro cronometrado1632 preguntas gratis con explicaciones y citas de ley, y luego un simulacro cronometrado completo.
¿Buscas una licencia específica? La mayoría también aprueba un examen de oficio. Práctica gratis para los principales:
¿Licencia fuera de California? Cubrimos cada estado con examen estatal real — 20 estados + NASCLA. Encuentra tu estado →
Cómo aprobar el examen CSLB de Derecho y Negocios
Empieza con la práctica rápida gratis de 10 preguntas — unos 5 minutos, cada respuesta explicada. Luego recorre los tres pasos de arriba hasta superar de forma constante el 70 % en un simulacro cronometrado completo — nuestro umbral de práctica para nuestro propio banco, no la puntuación de aprobación del examen, que CSLB no publica.
Pruebe una pregunta de muestra
¿Un contratista con licencia Clase "B" de Contratista General de Construcción puede realizar trabajo en cuál situación?
Not sure you even need a license? CSLB contractor license vs handyman — compare →
Preguntas de práctica de ejemplo
Algunas preguntas reales de este banco gratuito, con explicaciones completas. Usa la herramienta de arriba para el banco completo.
- 1. Organización y Licencias
¿Un contratista con licencia Clase "B" de Contratista General de Construcción puede realizar trabajo en cuál situación?
- a.Enmarcado, techos y paneles de yeso en una casa nueva
- b.Solo nivelar y pavimentar un estacionamiento
- c.Solo instalar un nuevo tablero eléctrico
- d.Solo reemplazar tuberías de agua subterráneas
Respuesta: a
Explicación: Un titular de licencia Clase B puede tomar contratos para estructuras y puede realizar por cuenta propia dos o más oficios de subcontratistas no relacionados. Instalar solo un panel eléctrico o reemplazar tuberías de agua requiere licencias especializadas Clase C, y nivelar/pavimentar es trabajo Clase A.
Fuente: Bus. & Prof. Code §7057
- 2. Finanzas Comerciales
Un contratista gana un trabajo por $300,000 e incurre en costos totales de $264,000. ¿Cuál es el margen de ganancia sobre el precio de venta?
- a.13.6%
- b.10%
- c.12%
- d.36%
Respuesta: c
Explicación: Ganancia = $300,000 − $264,000 = $36,000. Margen = Ganancia ÷ Precio de Venta = $36,000 ÷ $300,000 = 0.12 = 12%.
- 3. Contratos y Ejecución
Bajo la Ley del Derecho a Reparar de California (Civil Code §895 y siguientes, promulgada por SB 800), ¿cuál es el estatuto de limitaciones general para que un propietario presente un reclamo por defectos de construcción contra el constructor por un defecto de función/uso no especificado de otra manera?
- a.Cuatro años para defectos patentes y diez para latentes, bajo el CCP §337.15
- b.Un año desde el cierre de escrow, el plazo de la garantía de acabados
- c.Tres años desde el descubrimiento del defecto, bajo el estatuto general de daños
- d.Diez años desde la terminación sustancial, con plazos más cortos para categorías específicas
Respuesta: d
Explicación: El Civil Code §941(a) fija el límite externo de una demanda bajo la Ley del Derecho a Reparar en 10 años después de la terminación sustancial. Dentro de esa ventana, el §896 da a muchos tipos de defecto su propio plazo más corto — 4 años para plomería y alcantarillado, 5 para pintura y manchas, 1 para jardinería y riego, 2 para transmisión de ruido — de modo que la respuesta es escalonada, no un solo número. (a) es el marco PREVIO a SB 800 del Code of Civil Procedure §337.15, que aún rige proyectos fuera de la Ley pero no es el esquema del §896 que pregunta este ítem. (b) confunde el plazo de prescripción con la garantía expresa de un año sobre acabados que el constructor debe dar bajo el Civil Code §900. (c) aplica la regla general de tres años desde el descubrimiento para daño a bienes raíces (CCP §338(b)), que SB 800 desplazó para la construcción residencial cubierta.
Fuente: Civil Code §896, §941; cf. Civil Code §900, Code Civ. Proc. §337.15, §338(b)
- 4. Empleo
A staffing agency employs temporary workers assigned to a contractor. How often must the staffing agency generally pay these temporary employees under Labor Code §201.3?
- a.Monthly, on a designated payday each month
- b.Whenever the client contractor pays the agency
- c.At the end of each assignment, however long
- d.Weekly, whatever day the assignment happens to end
Respuesta: d
Explicación: Labor Code §201.3(b)(1) requires a temporary services employer to pay its assigned employees weekly, with the prior week's wages due on a regular designated payday, regardless of when the assignment ends. (b) is the pay-when-paid practice the section was written to stop - the agency's duty to its employees does not depend on the client remitting the invoice, and Labor Code §2810.3 can put the client contractor on the hook for those wages anyway. (c) holds the money to the end of the assignment, which on a long job could mean months. (a) applies the ordinary §204 rhythm, which is itself twice monthly rather than monthly, and in any case is displaced here by §201.3. Day-to-day and same-day assignments have their own rules in §201.3(b)(4)-(5).
Fuente: Labor Code §201.3(b)(1)
- 5. Seguridad
Before entering a permit-required confined space, the entry permit must document that the atmosphere has been tested. Which is typically tested FIRST?
- a.Flammables, then oxygen, then toxics
- b.Toxics, then oxygen, then flammables
- c.Oxygen, then toxics, then flammables
- d.Oxygen, then flammables, then toxics
Respuesta: d
Explicación: Pre-entry testing runs oxygen first, then combustible gases and vapours, then toxic contaminants, and the order is set by the instruments rather than by which hazard is worst. Most combustible gas sensors are catalytic and need oxygen to burn the sample: in an oxygen-deficient atmosphere they read low or read nothing, so a flammables-first result (a) can be falsely reassuring. Oxygen is also the reading that changes how the others are interpreted, since enrichment widens the flammable range while deficiency is immediately dangerous to life on its own. Toxics come last because that sensor is least affected by the other two. Both (b) and (c) put the toxic reading ahead of the flammable one and lose the safeguard.
Fuente: 8 CCR §5157(d)(5)(iii); 29 CFR 1926.1204(e)
Recursos útiles
Apply / register — CSLB (official) →- NASCLA Contractor's Guide to Business, Law and Project Management
The industry-standard business & law reference behind state contractor exams.
Ver en Amazon → - Construction Master Pro Calculator
The go-to construction-math calculator pros use on the job and on exam day.
Ver en Amazon →
Esta sección contiene enlaces de afiliados. Como Afiliado de Amazon, PrepPass gana con las compras que califican. Podemos ganar una comisión si compras a través de ellos, sin costo adicional para ti.
Más videos de CSLB
Suscríbete en YouTube →CSLB Law & Business Practice Test 2026 | Part 2 (50Q)
Pass the CSLB Law & Business Exam — Contracts Explained (2026)
Pass the CSLB Law & Business Exam — Public Works Explained (2026)
Contracts, payment & labor-law questions
Ve directo a una pregunta resuelta con la respuesta y una explicación completa.
- ¿Quién determina las tarifas de salario prevaleciente en los proyectos de obras públicas de California?
- Según la ley de California, se requiere un contrato de mejoras del hogar para trabajo residencial cuando el precio total del contrato (mano de obra Y materiales) sea al menos:
- Las leyes de pago oportuno de California están diseñadas principalmente para:
- Una "Solicitud y Certificado de Pago" estilo AIA (comúnmente G702/G703) se usa para:
- Un contratista cambia la dirección comercial y el número de teléfono principal del negocio con licencia. Con respecto al CSLB, el contratista debe:
Preguntas frecuentes
¿Cuántas preguntas de práctica de CSLB Law & Business hay en este banco?
1,632 preguntas de práctica originales que abarcan los 7 temas del examen CSLB Law & Business, con explicaciones completas y citas de estatutos de California en cada pregunta.
¿Es gratis la práctica de CSLB Law & Business?
Sí — cada pregunta de práctica, organizada por tema y con explicaciones completas, es gratis y sin registro. El examen simulado completo y cronometrado (puntuación de preparación en el simulacro, informe PDF y reintento de áreas débiles) también es gratis. Ninguna parte de la práctica es de pago. Aparte, PrepPass vende descargas opcionales — la guía de estudio de CSLB Law & Business, un cuadernillo de repaso imprimible y paquetes que los combinan — que nunca necesitas para practicar.
¿Son estas las preguntas reales del examen CSLB?
No. Todas las preguntas son 100% originales, redactadas a partir de fuentes de dominio público (California Business and Professions Code, Civil Code, Labor Code, Title 16 CCR). Nunca copiamos del examen real de CSLB ni de proveedores de preparación de pago.
¿Qué temas cubre el examen CSLB Law & Business?
Siete temas: Business Organization & Licensing, Business Finance, Employment Requirements, Insurance & Liens, Contracts & Performance, Public Works y Safety.
¿Cuál es la nota de aprobación del examen CSLB Law & Business?
CSLB no publica ninguna. Dice que en el centro de examen te informarán qué porcentaje de respuestas correctas necesitas, y que ese porcentaje varía según el examen; a quien aprueba nunca se le muestra su puntuación. CSLB tampoco publica el número de preguntas: los proveedores de preparación citan cifras para ambas cosas, y son suyas, no de CSLB. Lo que CSLB sí publica es la duración: 3.5 horas en un centro PSI.
¿Puedo tomar el examen CSLB en español?
Sí — el examen oficial de CSLB se ofrece en inglés y español. Otros idiomas pueden estar disponibles por solicitud de traductor (4–6 semanas de anticipación). Las preguntas de práctica de PrepPass están disponibles en inglés, 中文 y Español.
¿PrepPass guarda las preguntas que respondo mal?
Sí — regístrate gratis y el filtro 'Mis errores' te muestra solo las preguntas que has fallado en todas tus sesiones de práctica. Se actualiza automáticamente a medida que las vuelves a intentar y las aciertas.
Exámenes relacionados
Otros exámenes de licencia y certificación que la gente prepara junto con este.
- CSLB General Building (B) Trade
- CSLB Electrical (C-10) Trade
- CSLB Plumbing (C-36) Trade
- OSHA 30 Construction
- Master Plumber (UPC/IPC)