Network OperationsPregunta 52 de 100
Which change management step should occur before implementing a major network change?
a.Immediately push the change during peak hours
b.Skip documentation to save time
c.Disable all monitoring during the change
d.Obtain approval and prepare a rollback plan
Explicación
Sound change management requires securing approval and preparing a rollback plan so the change can be reversed if problems arise. Documentation and scheduling during maintenance windows reduce risk. Skipping these steps increases the chance of prolonged outages.
Practica las 100 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- What is the primary purpose of establishing a performance baseline for a network?
- Which agreement defines the guaranteed uptime and response times a service provider commits to deliver?
- An operations team uses a port on a switch to capture all traffic passing through other ports for analysis. What is this feature called?
- Which type of backup site is fully equipped and running, allowing near-immediate failover during a disaster?
- In monitoring terminology, what does SNMP use to send an unsolicited alert from a device to the management station?
- Which metric expresses the actual rate of successful data delivery over a link, as opposed to its rated capacity?
Última revisión: · proceso editorial
Equipo Editorial de PrepPass · Verificado con CompTIA Network+ (N10-009) · Cómo revisamos