Organización y LicenciasPregunta 1424 de 1605
A home improvement contractor may collect progress payments in what manner?
a.Payments that do not exceed the value of work performed or material delivered
b.All money up front
c.Double the value of work done
d.Only after full completion
Explicación
Under B&P Code section 7159.5, after the down payment, payments requested may not exceed the value of work performed or materials delivered. This prevents contractors from getting too far ahead of the work.
Referencia Legal: B&P Code §7159.5Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A consumer is harmed by a licensed contractor's abandonment of a job. Which financial protection may the consumer make a claim against?
- Which contract type is specifically governed by the detailed disclosure and formatting rules of the Home Improvement Business chapter?
- For purposes of the Home Improvement Business chapter, a 'home improvement' includes which of the following?
- The disclosure statements required in certain contracts, informing consumers about the CSLB and mechanics liens, serve what purpose?
- Which experience would best satisfy the four-year requirement for a Class C-27 Landscaping license?
- An applicant fails the trade or law portion of the licensing examination. What is the general consequence?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)