Framing & StructuralCâu 355 / 700

Fiber-cement lap siding is installed on a wood-framed wall. What clearance is generally required between the bottom edge of the siding and the finished grade or a roof surface below it?

a.No clearance; siding may touch the ground
b.A clearance (commonly around 6 inches to earth and about 1 to 2 inches above a roof) to keep the siding out of standing water and splash
c.At least 12 inches above a roof
d.Siding must be buried 2 inches into the grade

Giải thích

Manufacturers and the code call for clearance at the bottom of fiber-cement (and most) siding, commonly about 6 inches to earth and roughly 1 to 2 inches above roof surfaces, to keep the siding out of standing water and splash that would wick moisture. No clearance, 12 inches above a roof, or burying the siding are incorrect.

Trích dẫn luật: 2025 CA Residential Code §R703.3

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi