When notching or boring a solid-sawn floor joist for a pipe, which limitation applies to protect the joist's strength?
a.Notches may be any depth as long as they are on the top edge
b.Notches at the ends may not exceed one-fourth of the joist depth, and notches are not permitted in the middle third of the span
c.Bored holes may be located anywhere and up to half the joist depth
d.A hole may be drilled within 1 inch of the joist edge
Giải thích
To keep bending strength, end notches are limited to one-fourth the joist depth and no notches are allowed in the middle third where bending stress peaks; bored holes are limited to one-third the depth and kept back from edges. Unlimited notch depth, half-depth holes anywhere, or drilling within an inch of the edge all weaken the joist beyond code limits.
Trích dẫn luật: 2025 CA Residential Code §R502.8.1Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- In conventional wall framing, where two members of a double top plate are spliced (joints occur), the upper and lower plate joints must be offset by at least how much?
- Behind most exterior siding on a wood-framed wall, the code requires a water-resistive barrier equivalent to at least what?
- A roof is designed with a 4:12 slope (4 inches of vertical rise for every 12 inches of horizontal run). If the horizontal run from the wall to the ridge is 15 feet, what is the total vertical rise?
- Fasteners and metal connectors that contact preservative (pressure) treated deck lumber must have what property to prevent premature failure?
- In braced-wall and shear-wall construction resisting seismic loads, anchor bolts at the sill plate are commonly required to have what added component for load transfer?
- A roof rises 3 inches for every 12 inches of horizontal run. Expressed as a percentage, what is the slope of this roof?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra