Planning & EstimatingCâu 507 / 700
A supplier quotes framing lumber at $650 per thousand board feet (MBF). A job requires 8,000 board feet. What is the estimated material cost before tax?
a.$3,250
b.$5,200
c.$650
d.$52,000
Giải thích
Price is $650 per 1,000 board feet. For 8,000 board feet: 8,000 / 1,000 = 8 units, times $650 = $5,200. Option d multiplies by 8,000 instead of 8. Option a uses half the quantity. When pricing is quoted per MBF, divide the total board feet by 1,000 before multiplying by the unit price.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A parking lot is 200 ft by 300 ft and will receive 3 inches of asphalt. Approximately how many cubic yards of compacted asphalt are needed?
- When performing a quantity takeoff from a set of plans, which practice BEST reduces costly estimating errors?
- A project must meet CALGreen construction waste requirements. What is the general contractor's BEST approach to demonstrate compliance during the job?
- A general contractor coordinates multiple subcontractors on a commercial project. Which practice BEST prevents schedule conflicts and duplicated work between trades?
- A room measures 14 ft by 16 ft with 9 ft high walls. You must apply two coats of paint to the walls only. Deducting one 3 ft x 7 ft door and two 3 ft x 4 ft windows, and assuming coverage of 350 sq ft per gallon per coat, what is the MINIMUM whole number of gallons to buy?
- A room is 12 ft by 20 ft with 8 ft ceilings. You will hang 4 ft by 8 ft gypsum board on all four walls and the ceiling, ignoring openings and waste. What is the MINIMUM number of full sheets needed?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra